The Welaunee Arch: A 1,227-Acre Development Now on Hold Until 2027

UPDATE — SEPT. 30, 2026: The applicant has requested that consideration of the Welaunee Arch Concept PUD be continued until 2027 to allow for “additional community engagement on the proposal.” The City anticipates public hearings will resume in Spring 2027.

A proposal that could shape the future of 1,227 acres in northeast Tallahassee is moving through the City’s approval process. With public hearings now continued until 2027, residents will have additional time to learn about the proposal, ask questions and participate in the process.

The Welaunee Arch Phase 1 Concept Planned Unit Development (PUD) would establish the zoning framework for the West Arch and North Arch districts, located north of Interstate 10 and east of Centerville Road. Together, these districts make up 1,227 acres of the larger 4,778-acre Arch, and what happens here will help shape how much can be built and what types of development may be allowed in the remaining areas.

To be clear, this is not simply a subdivision. It is a master-planned community similar in scale to Southwood and nearly the same size as the two combined large developments already under construction in Welaunee – including the 500-acre Canopy development and 900-acre TalisTrails. Combined, these two Welaunee developments already underway add up to more than 3,400 residential units and approximately 1.25 million square feet of commercial, office and other nonresidential space.

What’s Being Proposed?

6,591

Residential Units

425,000 

Sq Ft of Commercial & Other Non-Residential Space

817 

Acres of Residential, Neighborhood or Mixed Use Development

395

Acres Identified as Open Space/Greenway*

*What does "Open Space/Greenway" mean?

Developers are often allowed to build at greater densities—more homes or commercial square footage per acre—by setting aside land as Open Space/Greenway. That can create the impression that large areas are being preserved for wildlife.

However, “Open Space/Greenway” does not necessarily mean undisturbed habitat. Under the proposed PUD, it includes not only conservation areas, but also parks, trails, community gathering places and stormwater management facilities. In other words, land may be cleared and graded for retention ponds or recreational uses while still counting toward the project’s Open Space/Greenway requirements.

What is Happening Now & Why This Decision Matters

The Welaunee Arch Concept PUD is currently on hold until 2027. On September 30, the applicant requested a continuance to allow for “additional community engagement on the proposal.” The City anticipates the public hearing process will resume in Spring 2027.

The application itself has not been withdrawn. The owner has submitted a Concept PUD for City approval. Once approved, it sets the basic rules for what can be built—including how many homes and how much commercial space are allowed, where development can occur, and how much land must remain open space or be protected.

These development rights are known as entitlements. Once granted, they can be extremely difficult to reduce or take away later.

Bottom line: Decisions made at this stage will shape what can be built, and the consequences of those decisions will be felt by residents for decades to come.

Where We Are in the Approval Process

July 13, 2026

Concept PUD Application Submitted

Proposed PUD submitted for City review

Sept. 14, 2026

DRC Review

Staff reviews and identifies required changes

Spring 2027

Solid white circle icon

Planning Commission Review

Planning Commission reviews the PUD and makes a recommendation to the Commission

TBD

City Commission Vote

Commission votes to approve or deny PUD

TBD

Final PUD Review

Staff verifies required conditions are satisfied

TBD

Subdivision & Site-Plan Review

Specific projects undergo detailed review

Development Review Committee (DRC) Gives Approval with Conditions

During their review on the concept PUD, staff identified several substantive issues. Members of the Development Review Committee met on Sept. 14 and recommended approval of the Welaunee Arch Concept PUD with a list of conditions that must be addressed before final approval. Read each division’s list of conditions using the buttons below.

Ways Staff Protected the Public’s Interest

City staff deserve credit for catching a number of important issues and adding conditions that better protect taxpayers, natural resources and our community.

  • Protected Utility Customers. Utility staff caught a roughly sevenfold discrepancy in commercial square footage used in a sewer calculation and required necessary onsite and off-site water/sewer extensions to be the developer’s responsibility.
  • Required Future Changes to Go Through the Proper Process. Staff  pushed back on language allowing development districts to shift later based on “market conditions” or “other factors,” requiring greater certainty about what is being approved and ensuring future changes go through the normal PUD amendment process, with opportunities for public review when required.
  • Held the Line on Natural Resources. Staff identified a proposed stormwater facility overlapping an old-growth live oak forest, exceptional specimen trees, Zone A floodplain and a potential karst feature—and required the final Natural Features Inventory (NFI) approval letter to be incorporated before final PUD adoption.
  • Kept Infrastructure Tied to Development. Staff required open space, stormwater, trails and transportation to keep pace with development—rather than allowing improvements to be pushed to the end, when responsibility can become much harder to enforce.
  • Preserved Walkability Standards. The PUD proposed exceptions to standards already established in the CAP. Staff required it to follow those standards, including street trees in residential subdivisions and stronger pedestrian, parking and usable green-space requirements.
  • Required the Bigger-Picture Stormwater Plan. The CAP already requires stormwater planning for the entire Arch at full buildout. Staff held the PUD to that requirement, requiring the master plan to be completed and approved before final PUD approval.

Where It Could Be Stronger

Staff addressed a number of important issues, but there are still areas where the PUD could provide greater clarity, accountability and protection.

  • Establish Who Pays Upfront. Water and sewer responsibilities are clear. The same clarity is needed for roads, intersections, stormwater, trails, parks and other public facilities: what is needed, when, and who pays for it?
  • Establish Measurable Infrastructure Triggers. Staff required infrastructure to keep pace with development, but the PUD could go further by tying key improvements to specific development milestones—such as establishing how many residential certificates of occupancy can be issued before the off-site sewer transport main to Capital Circle NE must be operational. This makes it clear what must be built, and by when, before additional development can proceed.
  • Define the 395 Acres of Open Space. Show how much is natural habitat, conservation land, wetlands/floodplain, stormwater, trails and usable parks—and whether protected natural areas form meaningful wildlife connections rather than isolated pieces.
  • Establish Conservation Earlier. Staff proposes waiting until subdivision or site-plan approval to finalize conservation easements and management plans so they can be based on more detailed information. But the CAP originally called for them before or concurrent with the PUD. Establishing the major conservation areas and wildlife connections earlier could help ensure that development is designed around them—not the other way around.
  • Show the Bigger Welaunee Picture. Explain how this PUD fits with previously approved and anticipated development so the public can understand the combined transportation, infrastructure, stormwater and open-space systems—and the costs and solutions associated with them.
Person reviewing architectural plans while working on a laptop at a drafting table.

Why Staff Review Matters

The current property owner has said there is no developer or buyer lined up for Welaunee Arch Phase 1. Instead, the owner is seeking approval of the PUD now, establishing the zoning framework that a future developer would inherit. Having those rules and development rights in place also creates greater certainty about what can be built—something that can add value when property is eventually marketed or sold.

Without a specific developer or project on the table, there is an incentive to preserve flexibility for whoever ultimately builds the property. But flexibility today can create uncertainty for the public tomorrow—particularly about infrastructure, environmental protections and who will ultimately pay for improvements needed to support development.

That’s why staff review at this stage matters so much. Ideally, substantive issues identified during review would be incorporated into a revised PUD before it moves forward, so the public and decision-makers can see exactly what is being approved. Instead, the DRC recommended approval with conditions, meaning many of staff’s required changes still must be incorporated or satisfied before final PUD approval.

The downside is that approval with conditions isn’t the same as incorporating the changes and reviewing the revised PUD before it moves forward. One change can have a ripple effect elsewhere in the plan. Reviewing the revisions together provides an opportunity to identify and address those effects before final approval.

Department Reports Listing Conditions

An Independent Perspective

Before staff’s conditions were made public, retired planner Scott Henderson independently identified many of the same concerns—and went farther in several areas. Scott shared a letter outlining his recommendations with the Development Review Committee members.

His recommendations included: looking at infrastructure needs across the Toe, Heel and Arch; establishing checkpoints to test transportation assumptions as development occurs; identifying land for schools, parks and fire/EMS early; clearly assigning responsibility for additional road capacity; strengthening functional open-space requirements; and establishing a comprehensive bicycle and trail network.

In his Sept. 20, 2026, opinion piece, “Will Tallahassee taxpayers foot the bill for growth?”, Scott discussed why the Arch PUD should undergo a comprehensive analysis along with why the City should impose a fair-share funding approach. Read it here.

Timeline: How We Got Here So Quickly & What’s Next

2020
2020

Welaunee Arch Master Plan Presented to the Public & Adopted

The City held a series of public meetings, workshops and charrettes to present the proposed Welaunee Arch Master Plan, answer questions and collect public input. Much of this engagement—including 11 charrettes—took place virtually during the COVID-19 pandemic before the Master Plan was adopted in November 2020.

June 23, 2026
June 23, 2026

Email Announcing Open House

Leon County Commissioner Brian Welch notified residents on his email list about an open house being held the following day by the landowner’s representatives.

View Email from Commissioner Welch

Update: A resident that lives near Welaunee shared she received a postcard about the Open House a month before the event.

June 24, 2026
June 24, 2026

Open House

At the open house, the owner’s representatives stated there were no immediate plans to develop this land nor buyers lined up to purchase the property. Attendees were shown a conceptual master plan and a project area map. This is the only public meeting I am aware of.

View Concept Plan Shown at Meeting
View General Location Map Shown at Open House

July 13, 2026
July 13, 2026

Zoning Application Submitted

The application to rezone the 1,227-acre PUD was submitted to the City by the landowner.

Although the Welaunee Arch PUD was listed as an agenda item online, basic information such as the size of the property, the type of rezoning requested or the Concept PUD document was not made accessible to the public. I obtained them by requesting the materials directly from the City.

•. View the City’s Site Map Where PUD was Posted
•  View the Information Provided Online
•.
View the Concept Plan Used in the Owner’s Application

August 3, 2026
August 3, 2026

PUD Review Added to the Development Review Committee Agenda

The Welaunee Arch PUD was included as an agenda item for the Aug. 10 Development Review Committee meeting.

View the Agenda 

August 10, 2026
August 10, 2026

Development Review Committee (DRC) Issues a Continuance

The project manager reported at the meeting that he had received at least 60 comments from the public—a remarkable number given that most residents had not known the rezoning would be considered until just days before the meeting.

The DRC continued the item until Sept. 14.

September 14, 2026
September 14, 2026

DRC Grants Approval with Conditions

The Welaunee Arch Concept Plan was approved with conditions and is moving forward to the Planning Commission.

The Tallahassee Democrat wrote about the decision in the article you can read here.

September 30, 2026
September 30, 2026

Planning Commission PUD Review Paused

The applicant requested that the Welaunee Arch Concept PUD be continued until 2027 to allow for “additional community engagement on the proposal.” The City anticipates public hearings will resume in Spring 2027 and will re-notice the hearings once new dates are set.

View the agenda notice of continuance here.

TBD
TBD

Planning Commission to Conduct PUD Review

Spring 2027 (Anticipated)

TBD
TBD

Ordinance Introduction at the City Commission

Date To Be Determined

TBD
TBD

City Commission Public Hearing & Vote

Date To Be Determined

What About Public Input?

UPDATE: On Sept. 30, the applicant requested that the Concept PUD be continued until 2027 specifically to allow for “additional community engagement on the proposal.” This creates an opportunity for residents to learn more about the proposal, ask questions and provide input before the public hearing process resumes.

City staff indicated that community meetings held in 2020 provided public input on the broader Welaunee Arch Master Plan. However, those meetings occurred approximately five years ago, had limited engagement due to COVID and did not present the detailed Concept PUD now under consideration.

Additionally, with construction already underway in two other developments inside Welaunee (Canopy & TalisTrails) 3,400 residential units and approximately 1.25 million square feet of commercial, office and other nonresidential space are either under construction or have been built, dramatically changing the number of people living nearby and the way traffic flows. These new conditions could dramatically impact what the public has to share.

Prior to the continuance, the Planning Department maintained that the 2020 community engagement was sufficient and pointed to the Development Review Committee (DRC) meeting as an opportunity for public comment. However, DRC meetings are not designed as a forum for questions and answers from the public. The applicant’s request for additional community engagement now creates an opportunity for that broader conversation before the public hearing process resumes.

Before the City Grants Zoning Approval for a Project of this Size, These Questions Should Be Considered

1. Do we have enough information to make the decision?

The City is being asked to approve the zoning framework for 1,227 acres before the Natural Features Inventory is complete and while stormwater planning and transportation analyses are still being completed or refined.

Bottom Line: These studies should inform the Concept Plan before zoning is approved—not afterward.

What is a Natural Features Inventory?

A Natural Features Inventory  or NFI is an environmental assessment that identifies wetlands, wildlife habitat and other sensitive natural features so they can be considered when planning development.

2. Should the City approve a plan that is vague?

The Concept Plan shows nearly 6,600 residential units and 425,000 square feet of commercial space. But those numbers are also labeled “informational only” and specifically do not represent the maximum development potential allowed under the proposed zoning.

That means the development ultimately built could potentially be substantially larger than the numbers the public and decision-makers are seeing today.

Bottom Line: Before zoning is approved, the plan should clearly state the maximum number of residential units and amount of commercial development the PUD would legally allow.

3. Does this plan honor the commitments made to the public?

One of the significant outcomes of the original Master Plan process was the negotiation over the preservation of wild spaces and a connected system of natural areas and greenways. If those protections were important enough to secure community support for the Master Plan, they should be clearly defined and protected in this PUD before zoning is approved.

Bottom Line: Before zoning is approved, the PUD should clearly identify how much land will remain protected natural area, where it will be located and whether those protections can later be reduced or moved without City Commission approval.

It’s Important to Note:

These questions are not about whether the development should or should not occur. They are about whether the public and decision-makers have enough information to make an informed zoning decision before development entitlements are granted.

Stay Involved

The applicant has requested additional time for community engagement before the Welaunee Arch Concept PUD returns to the public hearing process. This is an opportunity to learn more, ask questions and help identify issues that should be addressed before final decisions are made.

Before We Build TLH will share information about community meetings and new public hearing dates as they are announced.Check back for information about upcoming community meetings and opportunities to participate.

 

Questions Worth Asking

As community engagement moves forward, here are some important questions to consider:

  • How will the transportation impacts be addressed?
  • What does the completed Natural Features Inventory show?
  • Where will protected natural areas and wildlife corridors be located – and how many acres of that habitat will remain natural and permanently protected after full buildout?
  • How will stormwater be handled?
  •  Which protections negotiated during the Welaunee Arch Master Plan process are incorporated into this PUD?

Questions About the Development

Questions about the Welaunee Arch Concept PUD can be directed to the City project planner, Marcus Lloyd at Marcus.Lloyd@talgov.com or (850) 891.6445.

Bottom Line:

This is not a routine development application. It establishes the zoning framework for more than 1,200 acres and will influence future housing, commercial development, transportation and public infrastructure for years to come.

Much has changed since the original Welaunee Arch Master Plan was presented to the public in 2020, including development already underway in other parts of Welaunee.

The additional time for community engagement provides an opportunity for residents to better understand what is being proposed, review the documents, evaluate potential impacts and ask informed questions before the public hearing process resumes.

Sources

  • Welaunee Arch Phase 1 Concept Planned Unit Development (PUD) Submittal, July 2026, – View PDF
  • Residential, Commercial, Mixed Use and Open Space Numbers: Page 8 of the plan linked above
  • City’s Site Plan Agenda Map – The location where the PUD rezoning is listed, but additional details are not linked – View Website
  • Development Review Committee Meeting Agenda for August 10, 2026 – View PDF
  • Email from Commissioner Welch Announcing Open House, June 23, 2026 – View Screenshot
  • Concept PUD Map Shown at Open House, June 24, 2026 – View Image
  • General Location Map Shown at Open House on June 24, 2026 – View Image
  • Welaunee Arch Critical Area Plan – View PDF
  • PUD Approval Conditions:  Growth Management Department Conditions – View PDF  |  Planning Department Conditions – View PDF  |  Public Infrastructure Department Conditions – View PDF  |  Utility Department Conditions – View PDF
  • Planning Commission Agenda Notice of Continuance, Sept. 30, 2026 – View PDF